What is an example of applying cadence-based synchronization in SAFe?
A.
Using a Portfolio Kanban system
B.
Allocating budgets to Value Streams
C.
Creating cross-functional ARTs and Agile teams
D.
Conducting a PI Planning event
The Answer Is:
D
This question includes an explanation.
Explanation:
Conducting a PI Planning event is an example of applying cadence-based synchronization in SAFe. A PI Planning event is a two-day face-to-face or virtual meeting where all the members of an ART and Solution Train collaborate to align on a common vision, mission, and backlog, and plan the work for the next Program Increment (PI). A PI is a fixed timebox of 8 to 12 weeks that provides a regular cadence for delivering value. The PI Planning event is synchronized across all the teams and trains in the portfolio, and it occurs at the beginning of every PI. The PI Planning event enables the ART and Solution Train to achieve alignment, collaboration, synchronization, and commitment, as well as to identify and address risks and dependencies. References: = PI Planning - Scaled Agile Framework, Exam Study Guide: SP (6.0) - SAFe® Practitioner
SAFe-Practitioner PDF/Engine
Printable Format
Value of Money
100% Pass Assurance
Verified Answers
Researched by Industry Experts
Based on Real Exams Scenarios
100% Real Questions
Get 65% Discount on All Products,
Use Coupon: "ac4s65"