To manage non-functional requirements (NFRs) in the backlog
D.
To manage PI Objectives
The Answer Is:
A
This question includes an explanation.
Explanation:
One way Kanban boards are used in SAFe is to manage Work-In-Progress (WIP) limits. WIP limits are the maximum number of work items that can be in a given state or column of the Kanban board at any time. They help to prevent bottlenecks, reduce waste, improve flow, and increase quality and predictability. WIP limits are applied at every level of the SAFe framework, from the portfolio to the team, to optimize the value delivery123