According to the SAFe DevOps Practitioner 6.0 study guide and handbook, the Release activity is triggered by a business decision to go live. This means that the Solution is ready to be delivered to end users and customers, based on the validation and testing done in the previous activities. The handbook states that "The Release activity is triggered by a business decision to go live."1 Therefore, this activity involves releasing value to customers on demand, while also measuring and learning from the feedback.