Which event tracks the progress of the ART toward meeting the PI Objectives?
A.
ART Sync
B.
Portfolio minimum viable product (MVP) reviews
C.
Weighted Shortest Job First (WSJF) prioritization
D.
Incremental Business Value assignment
The Answer Is:
A
This question includes an explanation.
Explanation:
The ART Sync is a weekly event that brings together the representatives of the teams and stakeholders of an Agile Release Train (ART) to review the progress and status of the current Program Increment (PI). The ART Sync tracks the progress of the ART toward meeting the PI Objectives by using various metrics and indicators, such as the PI burnup chart, the team and ART predictability measures, the feature completion report, and the dependencies and risks status. The ART Sync also provides an opportunity to identify and resolve any impediments, issues, or blockers that may affect the PI delivery.
References:
ART Sync: This article from the Scaled Agile Framework explains the purpose, agenda, and participants of the ART Sync, and how it supports the alignment, collaboration, and execution of the ART.
PI Objectives: This article from the Scaled Agile Framework defines the concept and attributes of PI Objectives, and how they can be used to align and measure the outcomes of an ART or Solution Train.
SAFe-APM PDF/Engine
Printable Format
Value of Money
100% Pass Assurance
Verified Answers
Researched by Industry Experts
Based on Real Exams Scenarios
100% Real Questions
Get 65% Discount on All Products,
Use Coupon: "ac4s65"