What criterion must be satisfied before a Feature can flow from the analysis state to...

What criterion must be satisfied before a Feature can flow from the analysis state to the backlog state on an ART Kanban?

A.

The Feature is integrated and deployed

B.

The Feature is decomposed into Stories

C.

Teams define the build and test Solution

D.

The benefit hypothesis and acceptance criteria are defined