Who prepares the submittals that are reviewed and approved to ensure that the clients design...

Who prepares the submittals that are reviewed and approved to ensure that the clients design criteria is met in regards to material selection?

A.

General Contractor

B.

ICT distribution designer

C.

Client

D.

Architect. Engineering, Consultant Team