Weekend Sale Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: ac4s65

The program sponsor returns from a board of directors meeting alter identifying a significant risk...

The program sponsor returns from a board of directors meeting alter identifying a significant risk to the program schedule. This may Impact the program's benefits realization

What should the program manager do next?

A.

Update the program benefits management plan and risk register

B.

Implement the mitigation plan for the identified risk

C.

Adjust the program scope to avoid the risk

D.

Document the risk and create a mitigation plan

RCDDv14 PDF/Engine
  • Printable Format
  • Value of Money
  • 100% Pass Assurance
  • Verified Answers
  • Researched by Industry Experts
  • Based on Real Exams Scenarios
  • 100% Real Questions
buy now RCDDv14 pdf
Get 65% Discount on All Products, Use Coupon: "ac4s65"