An aircraft manufacturer is engaged by an airline to build a fleet of new airliners.

An aircraft manufacturer is engaged by an airline to build a fleet of new airliners. The program charter has been approved but the stakeholders are concerned that the delivery method of the program may not meet their expectations

Using the program master schedule what will the program manager incorporate to align the program with the expectations of the stakeholders?

A.

Program work breakdown structure (PWBS) program scope statement, and benefits management plan

B.

PWBS, benefits management plan, and program financial management plan

C.

Program charter PWBS, and program scope statement

D.

Program scope statement benefits management plan, and program financial management plan

RCDDv14 PDF/Engine
  • Printable Format
  • Value of Money
  • 100% Pass Assurance
  • Verified Answers
  • Researched by Industry Experts
  • Based on Real Exams Scenarios
  • 100% Real Questions
buy now RCDDv14 pdf
Get 65% Discount on All Products, Use Coupon: "ac4s65"