A program manager for the construction of a ship reviews the program management plan with...

A program manager for the construction of a ship reviews the program management plan with a shipyard representative. The shipyard representative indicates that while 65 percent progress was anticipated only 60 percent has been achieved

What should the program manager do to ensure benefits realization?

A.

Conduct a program performance analysis based upon the deviation, and update the program business case to reflect the schedule delay

B.

Inform the program sponsor and the steering committee of the delay, and validate the program business case

C.

Analyze the impact of the delay, review risks, identify any corrective actions, and update the benefits management plan

D.

Update the program schedule, and escalate the issue to the program management office (PMO) to accelerate shipyard work.

RCDDv14 PDF/Engine
  • Printable Format
  • Value of Money
  • 100% Pass Assurance
  • Verified Answers
  • Researched by Industry Experts
  • Based on Real Exams Scenarios
  • 100% Real Questions
buy now RCDDv14 pdf
Get 65% Discount on All Products, Use Coupon: "ac4s65"