A new program manager joins a mufti-year program that has been underway for almost a...

A new program manager joins a mufti-year program that has been underway for almost a year. During interviews, several stakeholders state that they do not understand how the program will help the organization

At the next stakeholder meeting, what should the program manager present to address their concerns?

A.

Program charter

B.

Program scope assessment results

C.

Business case and program roadmap

D.

Expected program benefits management plan