A company wants to perform a preliminary stakeholder analysis lo assess a new program's support.

A company wants to perform a preliminary stakeholder analysis lo assess a new program's support. What should the program manager develop'?

A.

Program communications management plan and the stakeholder charter

B.

Responsible accountable consult and inform (RACI) matrix stakeholder list, and escalation process

C.

Stakeholder strengths weaknesses, opportunities and threats (SWOT) analysis

D.

Stakeholder engagement plan, stakeholder register, and stakeholder map