The chief executive officer (CEO) informs the program manager that the delivery dale for protect...

The chief executive officer (CEO) informs the program manager that the delivery dale for protect A must be compressed by two months to accommodate market needs Project A relies upon deliverables from projects B and C.

Which of the following should the program manager do first?

A.

Direct the three project managers to crash their projects to allow project A the two months of scheduling needed

B.

Review the program resource management plan with the three project managers emphasizing their critical paths and shared critical resources to understand the possibility of accelerating the schedule

C.

Convene the change board to evaluate the cost benefit of the compression and the impact on the overall program

D.

Engage the executive sponsor and program board to evaluate the CEO's request and determine if the project manager should act on it

RCDDv14.1 PDF/Engine
  • Printable Format
  • Value of Money
  • 100% Pass Assurance
  • Verified Answers
  • Researched by Industry Experts
  • Based on Real Exams Scenarios
  • 100% Real Questions
buy now RCDDv14.1 pdf
Get 75% Discount on All Products, Use Coupon: "ac75sure"