A program manager is identifying and verifying risks as outlined in the risk management plan.

A program manager is identifying and verifying risks as outlined in the risk management plan. The results will be recorded in which of the following?

A.

Risk register

B.

Risk monitoring and control

C.

Risk response planning

D.

Risk mitigation strategy