A component is scheduled to close at the end of the week.

A component is scheduled to close at the end of the week. What should the program manager verity prior to allowing the component to close?

A.

The component has released resources to meet program objectives

B.

The component has met the quality requirements to meet program objectives

C.

The component has met the schedule requirements to meet program objectives

D.

The component has met the benefits realization criteria to meet program objectives