What typically happens if Product Backlog items are not sufficiently clear during SprintPlanning?

What typically happens if Product Backlog items are not sufficiently clear during Sprint

Planning?

(choose the best answer)

A.

Nothing, so long as the Product Owner gives the Developers a clear Sprint Goal.

B.

The Developers will have difficulty creating a forecast of work for the Sprint.

C.

Nothing in particular.

D.

The Scrum Master should not allow this to happen. Look for a new Scrum Master and

re-start the Sprint.

E.

The meeting is cancelled so refinement can be done first.