The only person who can abnormally terminate a Sprint is?
(choose the best answer)
A.
The Developers.
B.
The Scrum Master.
C.
The Product Owner.
D.
The Stakeholders.
The Answer Is:
C
This question includes an explanation.
Explanation:
The Scrum Guide specifies that only the Product Owner has the authority to cancel a Sprint. This is because the Product Owner is responsible for maximizing the value of the product and may decide to cancel a Sprint if the Sprint Goal becomes obsolete or if they foresee that the current direction will not lead to a valuable outcome