After the customer completes acceptance testing of the first Sprint.
B.
Once the architectural changes for the second Sprint are approved by the seniorarchitect.
C.
Immediately after the first Sprint.
D.
After the Product Backlog items for the second Sprint have been selected.
The Answer Is:
C
This question includes an explanation.
Explanation:
Sprints are fixed-length events of one month or less that serve as a container for the other Scrum events and activities. Sprints have consistent durations throughout a development effort. A new Sprint starts immediately after the conclusion of the previous Sprint. There is no gap or downtime between Sprints. The second Sprint starts right after the first Sprint, regardless of the customer acceptance testing, the architectural changes, or the Product Backlog items.
The Scrum Guide
Understanding and Applying the Scrum Framework
Professional Scrum Product Owner™ I Certification
PSPO-I PDF/Engine
Printable Format
Value of Money
100% Pass Assurance
Verified Answers
Researched by Industry Experts
Based on Real Exams Scenarios
100% Real Questions
Get 65% Discount on All Products,
Use Coupon: "ac4s65"