In the middle of the Sprint, the customer decides that there are two new features...

In the middle of the Sprint, the customer decides that there are two new features she wants.

The Product Owner could:

(choose the best two answers)

A.

Introduce these features at the next Daily Scrum.

B.

Ask the Developers to consider whether they can add these features to thecurrent Sprint without endangering the Sprint Goal.

C.

Add these features to the Product Backlog.

D.

Have the Scrum Master add these features to the current Sprint.