How much of the Sprint Backlog must be defined during the Sprint Planning event?

How much of the Sprint Backlog must be defined during the Sprint Planning event?

(choose the best answer)

A.

Just enough to understand design and architectural implications.

B.

Enough so the Developers can create their forecast of what work they can do.

C.

The entire Sprint Backlog must be identified and estimated by the end of Sprint Planning.

D.

Just enough tasks for the Scrum Master to be confident in the Developers ' understanding of the Sprint.