During the Sprint Retrospective a Scrum Team has identified several high priority processimprovements.

During the Sprint Retrospective a Scrum Team has identified several high priority process

improvements. Which of the following statements is most accurate?

(choose the best answer)

A.

The Scrum Team may add the items to the Sprint Backlog for the next Sprint.

B.

The Scrum Team should decline to add a process improvement to the Sprint Backlog

when things are running smoothly.

C.

The Scrum Team should choose at least one high priority process improvement to

place in the Product Backlog.

D.

The Scrum Master selects the most important process improvement and places it in

the Sprint Backlog

PSPO-I PDF/Engine
  • Printable Format
  • Value of Money
  • 100% Pass Assurance
  • Verified Answers
  • Researched by Industry Experts
  • Based on Real Exams Scenarios
  • 100% Real Questions
buy now PSPO-I pdf
Get 65% Discount on All Products, Use Coupon: "ac4s65"