Weekend Sale Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: ac4s65

You are the Scrum Master for four teams working from the same Product Backlog.

You are the Scrum Master for four teams working from the same Product Backlog. Several of the Developers come to you complaining that work identified for the upcoming two Sprints will require full time commitment from Phil, an external specialist. As the Scrum Master what should you do to solve this upcoming problem?

(choose the best answer)

A.

Prepare the Sprint Backlogs each day tor the teams so Phil can spend some time in each team.

B.

Allocate Phil to one team per Sprint, so that over tour Sprints every team will have had the support It requires.

C.

As needed, consult with the Developers on now they want to manage this problem and help them implement their preferred solution.

D.

Ask Phil tor a plan to hire and train additional people in nis domain, and in the meantime work with the Product Owner and Developers to re-prioritize the work so that tasks not depending on Phil can be done first.

PSM-II PDF/Engine
  • Printable Format
  • Value of Money
  • 100% Pass Assurance
  • Verified Answers
  • Researched by Industry Experts
  • Based on Real Exams Scenarios
  • 100% Real Questions
buy now PSM-II pdf
Get 65% Discount on All Products, Use Coupon: "ac4s65"