Which two things should the Scrum Team do during the first Sprint?
(choose the best two answers)
A.
Define the major product features and a release plan architecture.
B.
Build at least one piece of valuable functionality.
C.
Create at least one valuable, useful Increment
D.
Make up a plan tor the rest of the project
E.
Analyze, describe, and document the requirements for the subsequent Sprints.
The Answer Is:
B, C
This question includes an explanation.
Explanation:
According to the Scrum Guide, two things that the Scrum Team should do during the first Sprint are building at least one piece of valuable functionality and creating at least one valuable, useful Increment. These are the goals of every Sprint, regardless of its order. The other options are not things that the Scrum Team should do during the first Sprint, as they are either out of scope (such as defining major product features and a release plan architecture or making a plan for the rest of the project) or unnecessary (such as analyzing, describing, and documenting requirements for subsequent Sprints).
PSM-I PDF/Engine
Printable Format
Value of Money
100% Pass Assurance
Verified Answers
Researched by Industry Experts
Based on Real Exams Scenarios
100% Real Questions
Get 65% Discount on All Products,
Use Coupon: "ac4s65"