When must a Product Owner release each Increment? (Choose the best answer.)
A.
When it makes sense.
B.
When the Scrum Team finishes their work.
C.
Whenever the product is free of defects.
D.
After every Sprint, Without exception.
The Answer Is:
A
This question includes an explanation.
Explanation:
A Product Owner releases each Increment when it makes sense, as stated in [2]: “The Product Owner decides when to release an Increment. This can be done at any time during or after a Sprint. The Product Owner may choose to release an Increment when it delivers enough value to customers or users, when it meets a market opportunity, when it reduces risk or uncertainty, or when it aligns with other business goals.”