When is a Product Backlog item considered complete? (choose the best answer)
A.
When the item passes ail acceptance criteria
B.
When the item has gamed product sponsor approval
C.
At the end of the Sprint
D.
When the item meets the Definition of Done
The Answer Is:
D
This question includes an explanation.
Explanation:
A Product Backlog item is considered complete when it meets the Definition of Done, as stated in [5]: “When a Product Backlog item or an Increment is described as “Done”, everyone must understand what “Done” means. Although this varies significantly per Scrum Team, members must have a shared understanding of what it means for work to be complete, to ensure transparency. This is the definition of “Done” for the Scrum Team and is used to assess when work is complete on the product Increment.”
PSM-I PDF/Engine
Printable Format
Value of Money
100% Pass Assurance
Verified Answers
Researched by Industry Experts
Based on Real Exams Scenarios
100% Real Questions
Get 60% Discount on All Products,
Use Coupon: "8w52ceb345"