What two factors are best considered when establishing the Sprint length? (Choose two.)
A.
The organization has mandated similar length sprints.
B.
The level of uncertainty over the technology to be used.
C.
The frequency at which team formation can be changed.
D.
The risk of being disconnected from the stakeholders.
The Answer Is:
B, D
This question includes an explanation.
Explanation:
The correct answers are B and D, because the length of the Sprint should be chosen based on the level of uncertainty over the technology to be used and the risk of being disconnected from the stakeholders. The Scrum Guide states that “Sprints have consistent durations throughout a development effort. A new Sprint starts immediately after the conclusion of the previous Sprint. Sprints enable predictability by ensuring inspection and adaptation of progress toward a Sprint Goal at least every calendar month. When a Sprint’s horizon is too long the Sprint Goal may become invalid, complexity may rise, and risk may increase.”
PSM-I PDF/Engine
Printable Format
Value of Money
100% Pass Assurance
Verified Answers
Researched by Industry Experts
Based on Real Exams Scenarios
100% Real Questions
Get 60% Discount on All Products,
Use Coupon: "8w52ceb345"