Short enough to keep the business risk acceptable to the Product Owner.
B.
Short enough to be able to synchronize the development work with other business events.
C.
No more than one calendar month.
D.
All of these answers are correct.
The Answer Is:
D
This question includes an explanation.
Explanation:
According to the Scrum Guide 1 , the heart of Scrum is a Sprint, a time-box of one month or less during which a “Done”, useable, and potentially releasable product Increment is created. Sprints have consistent durations throughout a development effort. A new Sprint starts immediately after the conclusion of the previous Sprint. The length of a Sprint should be short enough to keep the business risk acceptable to the Product Owner, short enough to be able to synchronize the development work with other business events, and no more than one calendar month.
[References: Scrum Guide, , , ]
PSM-I PDF/Engine
Printable Format
Value of Money
100% Pass Assurance
Verified Answers
Researched by Industry Experts
Based on Real Exams Scenarios
100% Real Questions
Get 65% Discount on All Products,
Use Coupon: "ac4s65"