It is used to congratulate the Development Team if it did what it forecast, or to punish the Development Team if it failed to meet its forecast.
B.
It is a demo at the end of the Sprint for everyone in the organization to check on the work done.
C.
It is a mechanism to control the Development Team’s activities during a Sprint.
D.
It is when the Scrum Team and stakeholders inspect the outcome of a Sprint and figure out what to do next.
The Answer Is:
D
This question includes an explanation.
Explanation:
The correct answer is D, because this statement best describes the Sprint Review. The Scrum Guide states that “a Sprint Review is held at the end of the Sprint to inspect the Increment and adapt the Product Backlog if needed. During the Sprint Review, the Scrum Team and stakeholders collaborate about what was done in the Sprint.” Therefore, the Sprint Review is when the Scrum Team and stakeholders inspect the outcome of a Sprint and figure out what to do next.
PSM-I PDF/Engine
Printable Format
Value of Money
100% Pass Assurance
Verified Answers
Researched by Industry Experts
Based on Real Exams Scenarios
100% Real Questions
Get 60% Discount on All Products,
Use Coupon: "8w52ceb345"