Within the same Kanban system, Work in Progress (WIP), is NOT a leading indicator for:(choose...

Within the same Kanban system, Work in Progress (WIP), is NOT a leading indicator for:

(choose the best answer)

A.

Throughput.

B.

Story points delivered.

C.

Cycle Time.

D.

Number of Product Backlog items finished in a Sprint.