A Service Level Expectation (SLE) consists of which two items?
(Choose the best two answers)
A.
A period of elapsed days.
B.
A cost of delay.
C.
A probability.
D.
A forecasted date.
The Answer Is:
A, C
This question includes an explanation.
Explanation:
An SLE combines a timeframe (elapsed days) and a probability, representing the likelihood that a work item will be completed within that timeframe. This helps to set realistic expectations for stakeholders and guide the team in maintaining a predictable flow. References: The Kanban Guide for Scrum Teams​.