The total amount of Work in Progress (WIP) for a specific date.
B.
The average Throughput for a specific date range.
C.
The Cycle Time for an item that completed on a specific date.
D.
The exact average Cycle Time for all items completed on a specific date.
The Answer Is:
A, C
This question includes an explanation.
Explanation:
A cumulative flow diagram (CFD) provides insights into the amount of WIP and helps track Cycle Time by showing how long items stay in each stage of the workflow. This visualization tool is valuable for teams using Scrum with Kanban as it highlights bottlenecks and helps manage flow through the stages of the workflow. References: The Kanban Guide for Scrum Teams​.