When is refinement of a Product Backlog item complete? (choose the best answer)
A.
When the Product Owner says it is ready.
B.
At the end of Sprint Planning.
C.
When the Scrum Team agrees it is precise enough.
D.
When the Product Backlog Refinement timebox expires.
The Answer Is:
C
This question includes an explanation.
Explanation:
Detailed Explanation: Refinement is complete when the Scrum Team agrees that the Product Backlog item is clear and precise enough to proceed with planning or implementation.