Scrum PSD Question Answer
How much time will there be after a sprint before the next one starts?
Enough to deploy the increment and update the product backlog based on the outcome of the sprint review
Enough to clean up lingering definition of done points
None, a new sprint starts immediately after the end of the previous one
At most a week for a one-month sprint
The scrum guide says: "A new Sprint starts immediately after the conclusion of the previous Sprint."