For this question, refer to the TerramEarth case study
You analyzed TerramEarth ' s business requirement to reduce downtime, and found that they can achieve a majority of time saving by reducing customers ' wait time for parts You decided to focus on reduction of the 3 weeks aggregate reporting time Which modifications to the company ' s processes should you recommend?