The project is in stage 3.

The project is in stage 3. The BuildyBrick construction teams are unsure about using the required environmentally friendly concrete technique. As the team has not used the technique before, the work could take longer than originally planned. The Regeneration Manager has arranged a visit to another site where the technique is being used.

Which principle is being applied, and why?

A.

Learn from experience, because a field trip provides an opportunity to learn from others

B.

Learn from experience, because lessons should only be reviewed at project start

C.

Manage by exception, because work package time tolerance may be exceeded

D.

Manage by exception, because the CEO should resolve the concern

Prince2-Practitioner PDF/Engine
  • Printable Format
  • Value of Money
  • 100% Pass Assurance
  • Verified Answers
  • Researched by Industry Experts
  • Based on Real Exams Scenarios
  • 100% Real Questions
buy now Prince2-Practitioner pdf
Get 65% Discount on All Products, Use Coupon: "ac4s65"