The project is approaching the end of stage 3, and stage 4 is being planned...

The project is approaching the end of stage 3, and stage 4 is being planned as part of the 'managing a stage boundary' process.

Which action should the project manager carry out as part of the 'update the project plan' activity?

A.

Include the actual time and cost of the work to prepare the 'marketing materials' in the project plan.

B.

Ensure that the team manager for the work package 'delivered pilot courses' is included as a resource.

C.

Update the project's business case to show any new key risks that have been identified.

D.

Include the tolerances for the work package 'delivered pilot courses' in the project plan.

Prince2-Practitioner PDF/Engine
  • Printable Format
  • Value of Money
  • 100% Pass Assurance
  • Verified Answers
  • Researched by Industry Experts
  • Based on Real Exams Scenarios
  • 100% Real Questions
buy now Prince2-Practitioner pdf
Get 65% Discount on All Products, Use Coupon: "ac4s65"