MANAGING PRODUCT DELIVERYStage 2 is in progress.

MANAGING PRODUCT DELIVERY

Stage 2 is in progress. While producing the team plan, the team manager responsible for the work package to develop the 'classroom-based training material' discovered that the representatives assigned to check the products were unsuitable.

Which action should the team manager take in response?

A.

Discuss the situation with project assurance.

B.

Advise the project manager of this risk.

C.

Update the quality register with these concerns.

D.

Raise an exception report to the project manager.