Whose approval is needed to replace a Stage Plan with an Exception Plan?
A.
Corporate or programme management
B.
Project Board
C.
Project Manager
D.
Team Manager
The Answer Is:
B
This question includes an explanation.
Explanation:
The approval needed to replace a Stage Plan with an Exception Plan must come from the Project Board. This is because the Exception Plan is created when a Stage Plan is forecast to exceed its tolerance levels, and the Project Board is responsible for approving such significant changes in the project’s direction or management. References: PRINCE2® Foundation official documentation and study materials.