Whitt is 3 purpose of the initiating a project’ process?
A.
To prepare the contract for the project to enable the project board to commit to delivery
B.
To provide the project board with Just Enough Information to decide whether to approve the Initiation stage
C.
To provide the opportunity for the senior user in confirm that they find the project product acceptable
D.
To enable the project board to empower the project manager to work within delegated authority limits
The Answer Is:
B
This question includes an explanation.
Explanation:
The purpose of the 'Initiating a Project' process is to provide the Project Board with just enough information to decide whether to approve the initiation stage. This process involves the development of a more detailed Business Case and Project Plan, which are crucial for the Project Board to assess the project's viability and decide on its initiation confidently. References: PRINCE2® official guide and syllabus.
Prince2-Foundation PDF/Engine
Printable Format
Value of Money
100% Pass Assurance
Verified Answers
Researched by Industry Experts
Based on Real Exams Scenarios
100% Real Questions
Get 65% Discount on All Products,
Use Coupon: "ac4s65"