Which theme estimates the cost of delivering the project?
A.
Business case
B.
Change
C.
Plans
D.
PROGEESS
The Answer Is:
C
This question includes an explanation.
Explanation:
The Plans theme in PRINCE2® estimates the cost of delivering the project. This theme involves the preparation and maintenance of the necessary schedules and budgets to control the project, including outlining how, when, and by whom the project's products will be delivered and at what cost.References: PRINCE2® 7 Foundation handbook and documents.