New Year Special - 75% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: ac75sure

The project manager needs to understand what makes the outputs acceptable to the users.

The project manager needs to understand what makes the outputs acceptable to the users.

In which step of the 'planning' technique should this occur?

A.

Defining and analysing the products

B.

Organizing work packages

C.

Preparing estimates

D.

Preparing a schedule