The project manager needs to document how risk management will be undertaken during the project.

The project manager needs to document how risk management will be undertaken during the project.

In which step of the 'risk management’ technique should the project manager document this?

A.

Identify: define context and objectives

B.

Identify: identify threats and opportunities

C.

Assess: prioritize risks

D.

Assess: combine risk profile