The project manager needs to confirm that operational teams are responsible for the running of...

The project manager needs to confirm that operational teams are responsible for the running of the outputs.

During which step of the ‘organizational design and development’ technique should the project manager ensure this?

A.

Manage the ongoing changes to the project ecosystem

B.

Transition the project into the organizational ecosystem

C.

Understand the organizational ecosystem

D.

Develop the project ecosystem