What is the minimum number of management stages required by PRINCE2?
A.
Two stages: to initiate and to deliver the project
B.
One stage: to cover the whole project
C.
Three stages: to initiate, to deliver and to close the project
D.
Four stages: to start, to initiate, to deliver and to close the project
The Answer Is:
A
This question includes an explanation.
Explanation:
PRINCE2® requires a minimum of two management stages for any project: one to initiate the project and another to deliver the project. This structure ensures proper planning, delegation, monitoring, and control over the course of the project lifecycle.References: = PRINCE2® 7 Foundation handbook and online resources