Which is an objective of the 'controlling a stage' process?
A.
To review the business justification for the project
B.
To replan the current stage when directed
C.
To develop products to defined quality criteria
D.
To produce a learn plan for the work package
The Answer Is:
B
This question includes an explanation.
Explanation:
An objective of the 'Controlling a Stage' process in PRINCE2® is to replan the current stage when directed. This process handles day-to-day management of the project, and includes responding to issues that might impact the stage plan, requiring replanning to ensure project objectives can still be met.References: PRINCE2® Foundation Manual