Which is a true statement about PRINCE2 event-driven controls?
A.
Event-driven controls take place at predefined periodic intervals
B.
Event-driven controls are produced at the frequency defined in a Work Package
C.
Event-driven controls are used for decision making
D.
Checkpoint Reports are event-driven controls
The Answer Is:
C
This question includes an explanation.
Explanation:
PRINCE2 defines event-driven controls as those that are triggered by the occurrence of certain events within the project lifecycle, such as the completion of a product or phase. These controls are essential for decision-making because they provide necessary information at key points, allowing project managers and the Project Board to make informed decisions about the future of the project. References: PRINCE2 Foundation manual, PRINCE2 official resources
Prince2-Foundation PDF/Engine
Printable Format
Value of Money
100% Pass Assurance
Verified Answers
Researched by Industry Experts
Based on Real Exams Scenarios
100% Real Questions
Get 65% Discount on All Products,
Use Coupon: "ac4s65"