To identify, assess and control any potential changes to the baseline
B.
To establish the project's structure of accountability
C.
To assess and control uncertainty
D.
To understand whether the targets are achievable
The Answer Is:
D
This question includes an explanation.
Explanation:
The purpose of the plans theme in PRINCE2® is to facilitate the management and control of the project by establishing whether the project's targets are achievable. This involves setting out how and when the project's objectives are to be achieved by defining the necessary resources, activities, timescales, and costs. References: PRINCE2® Foundation Handbook, Plans Theme section.