Which is a purpose of the Closing a Project process?
A.
Authorize the final stage of the project
B.
Confirm that all benefits defined in the Business Case have been achieved
C.
Recognize whether objectives set out in the original Project Initiation Documentation have been achieved
D.
Delegate day-to-day management of the end of the project to the Project Manager
The Answer Is:
C
This question includes an explanation.
Explanation:
The purpose of the Closing a Project process is to ensure that the objectives defined in the Project Initiation Documentation (PID) have been achieved. This process involves verifying that the project's deliverables meet the objectives and that the project has fulfilled its purposes as planned. References: PRINCE2® Foundation official study guide and materials.
Prince2-Foundation PDF/Engine
Printable Format
Value of Money
100% Pass Assurance
Verified Answers
Researched by Industry Experts
Based on Real Exams Scenarios
100% Real Questions
Get 65% Discount on All Products,
Use Coupon: "ac4s65"