If the Project Board instructs the Project Manager to implement a request for change, which...

If the Project Board instructs the Project Manager to implement a request for change, which document would contain details of that change?

A.

Checkpoint Report

B.

Highlight Report

C.

Issue Report

D.

Product Status Account