Which document should record the agreed amount of risk budget for a project?
A.
Project Brief
B.
Project Plan
C.
Risk Management Strategy
D.
Risk Register
The Answer Is:
C
This question includes an explanation.
Explanation:
The agreed amount of risk budget for a project is recorded in the Risk Management Strategy document. This document outlines how risks will be managed throughout the project, including the budget set aside specifically for implementing risk responses. It provides a structured approach to managing risks, including their identification, assessment, planning responses, and the funds allocated for these activities.References: PRINCE2® 7 Foundation handbook and documents.