The dates for the project's end stage assessment included in the project plan
B.
The expected frequency of progress reports specified in a work package
C.
The expected dates for planned checks of specialist products included in a stage plan
D.
The planned exception assessment meeting to authorize a requested exception plan
The Answer Is:
B
This question includes an explanation.
Explanation:
A time-driven control is defined as a monitoring system that is based on a fixed time interval, such as weekly or monthly progress reports. The expected frequency of progress reports specified in a work package represents a time-driven control, where updates are required at predefined intervals irrespective of the state of the project at those times.References: = PRINCE2® 7 Foundation handbook and online resources
Prince2-Foundation PDF/Engine
Printable Format
Value of Money
100% Pass Assurance
Verified Answers
Researched by Industry Experts
Based on Real Exams Scenarios
100% Real Questions
Get 65% Discount on All Products,
Use Coupon: "ac4s65"